Westinghouse Electric Company has signed a long-term contract with the Finland's Teollisuuden Voima Oyj (TVO) for in-service inspections of all three reactors at the Olkiluoto nuclear power plant.
- Source: NEI Magazine
- Date: Thursday, 12 March 2020
- Original article: neimagazine.com/news/newstvo-contracts-westinghouse-for-service-inspections-at-olkiluoto-nuclear-plant-7816421
GE announced on 4 March that it has been selected by Teollisuuden Voima (TVO) to continue providing maintenance services for Olkiluoto 1&2 in Finland for the duration of the lifetime of the reactors.
- Source: NEI Magazine
- Date: Friday, 06 March 2020
- Original article: neimagazine.com/news/newsge-to-provide-maintenance-services-to-finlands-olkiluoto-nuclear-plant-7808732
The loading of fuel into the core of the Olkiluoto 3 has been delayed until June next year because of slow progress of the system tests and shortcomings in spare part deliveries, the Areva-Siemens consortium has informed Finnish utility Teollisuuden Voima Oyj (TVO). Grid connection of the EPR is now scheduled for November, with the start of regular electricity production expected in March 2021.
- Source: World Nuclear News
- Date: Friday, 20 December 2019
- Original article: world-nuclear-news.org/Articles/System-tests-further-delay-Finnish-EPR-start-up
Commissioning of the Olkiluoto 3 EPR is now running six weeks behind schedule, the Areva-Siemens consortium has informed Finnish utility Teollisuuden Voima Oyj. The supplier is to provide TVO with a revised schedule for the start-up of the plant next month.
- Source: World Nuclear News
- Date: Saturday, 09 November 2019
- Original article: world-nuclear-news.org/Articles/Delay-in-final-checks-puts-back-Olkiluoto-EPR-star
Westinghouse Electric Company has signed a long-term contract with Finnish nuclear power company Teollisuuden Voima Oyj (TVO) for deliveries of nuclear fuel until 2038 for two boiling water reactors at units, 1 and 2 of the Olkiluoto nuclear plant.
- Source: NEI Magazine
- Date: Tuesday, 05 November 2019
- Original article: neimagazine.com/news/newstvo-signs-fuel-contract-with-westinghouse-for-olkiluoto-7487652
The first eight Westinghouse Triton11 fuel assemblies have been delivered to Finnish utility Teollisuuden Voima Oy's Olkiluoto plant. The new assemblies will be loaded into Olkiluoto 2 during the unit's upcoming outage.
- Source: World Nuclear News
- Date: Thursday, 28 February 2019
- Original article: world-nuclear-news.org/Articles/First-delivery-of-new-generation-BWR-fuel