“When building a machine as large and as complex as ITER, difficulties and setbacks do not come as surprises - they are an integral part of manufacturing, assembling and installing first-of-a-kind components,” the ITER Organisation said recently.
- Source: NEI Magazine
- Date: Friday, 25 November 2022
- Original article: neimagazine.com/news/newsiter-says-essential-key-components-repairs-will-impact-schedule-10381371
Iter said in a project update that the two components are the vacuum vessel thermal shields and the vacuum vessel sectors.
The issues “demand in-depth examination, creativity in devising corrective actions, and time and budget to repair”, Iter said.
The vacuum vessel thermal shields are actively cooled silver-plated elements, 20 mm thick that contribute to thermally insulating the plant’s superconducting magnet system operating at 4K, or minus 269C.
- Source: Nucnet
- Date: Thursday, 24 November 2022
- Original article: nucnet.org/news/eur20-billion-project-faces-delays-as-defects-found-in-two-key-first-of-a-kind-components-11-3-2022
The International Thermonuclear Experimental Reactor (ITER) project has announced defects have been discovered in the thermal shields and vacuum vessel sectors and warned that the consequences on schedule and cost "will not be insignificant".
- Source: World Nuclear News
- Date: Wednesday, 23 November 2022
- Original article: world-nuclear-news.org/Articles/Defects-found-in-two-key-components-of-ITER-tokama
Work has resumed at the underground US Waste Isolation Pilot Plant (WIPP) near Carlsbad in New Mexico after being closed for almost three years following a radiation leak in February 2014.
- Source: NEI Magazine
- Date: Friday, 06 January 2017
- Original article: neimagazine.com/news/newsus-wipp-waste-repository-resumes-operation-5711379