Georgia Power Company said in a filing with the US Securities and Exchange Commission on 19 March that the planned November start up of unit 3 at the Vogtle NPP in Georgia could be delayed by at least a month. Georgia Power said that its Southern Nuclear Operating Company “had identified, and is in the process of completing, additional construction remediation work, primarily related to electrical commodity installations, necessary to ensure quality and design standards are met as system turnovers are completed prior to starting hot functional testing and fuel load for Plant Vogtle unit 3”. As a result, Georgia Power now expects the start of hot functional testing to be delayed into April.
- Source: NEI Magazine
- Date: Friday, 26 March 2021
- Original article: neimagazine.com/news/newsmore-delays-for-us-vogtle-npp-8625857