Conditions at the Fukushima Daiichi nuclear power plant site have improved since a review in 2018, the International Atomic Energy Agency (IAEA) has concluded following its fifth review of Japan's plans and activities to decommission the plant. The IAEA team of experts reviewed the current situation at the site and future plans in areas such as the removal of used fuel and the retrieval of fuel debris, radioactive waste, water and site management.
- Source: World Nuclear News
- Date: Saturday, 28 August 2021
- Original article: world-nuclear-news.org/Articles/IAEA-sees-continued-progress-at-Fukushima-Daii-(1)
Recyclable-Fuel Storage Company Ltd (RFS) now expects its interim used fuel storage facility in Mutsu, Aomori prefecture, to begin operating in fiscal year 2023 (ending March 2024). Following several previous delays, the facility - construction of which began in 2010 - had been scheduled to start up later this year. However, the construction of additional safety measures is taking longer than expected.
- Source: World Nuclear News
- Date: Thursday, 29 July 2021
- Original article: world-nuclear-news.org/Articles/Start-up-of-Japanese-used-fuel-store-delayed
A review of the management of treated water stored at the damaged Fukushima Daiichi nuclear power plant in Japan has been carried out by the International Atomic Energy Agency (IAEA). It says the two options under consideration for disposing of this water - discharge into the sea and via vapour release - are both technically feasible.
- Source: World Nuclear News
- Date: Saturday, 04 April 2020
- Original article: world-nuclear-news.org/Articles/IAEA-supports-discharge-of-Fukushima-Daiichi-water
Japanese ministries and other organisations are working together - with the support of the International Atomic Energy Agency - to deliver the ultimate decontamination and decommissioning of the former Fukushima Daiichi nuclear power plant. Progress is being made to remove all used fuel and debris from units 1-3, while the challenge of removing large volumes of treated water stored at the site is being addressed, speakers told a side event at the 63rd IAEA General Conference.
- Source: World Nuclear News
- Date: Wednesday, 18 September 2019
- Original article: world-nuclear-news.org/Articles/Fukushima-decommissioning-moves-forward
Japan has made significant progress in decommissioning the damaged Fukushima Daiichi nuclear power plant, but many challenges remain, a mission by the International Atomic Energy Agency (IAEA) has concluded.
- Source: World Nuclear News
- Date: Wednesday, 14 November 2018
- Original article: world-nuclear-news.org/Articles/IAEA-reviews-Fukushima-Daiichi-clean-up-work