Filter by tags: Atomstroyexport Clear all tag filters
52 news articles found
Plants in Turkey and Bangladesh part of Moscow’s overseas portfolio
- Source: Nucnet
- Date: Saturday, 03 June 2023
- Original article: nucnet.org/news/atomstroyexport-completes-concrete-pouring-for-akkuyu-1-and-rooppur-2-containment-domes-6-5-2023
Installation of an internal shaft has been completed at unit 1 of the Rooppur NPP in Bangladesh. The shaft is made of austenitic stainless steel and is an integral part of the reactor. It weighs more than 73 tonnes with a length of more than 108 metres and a diameter is 3.61 metres. The in-vessel shaft is a part of the main elements of in-vessel devices. It contains a baffle and the fuel assemblies. The bottom of the shaft is perforated to allow the circulation of the coolant (double desalination water) the fuel elements.
- Source: NEI Magazine
- Date: Thursday, 01 June 2023
- Original article: neimagazine.com/news/newsvver-1200-internal-shaft-installed-at-rooppur-1-10901569
Egypt's nuclear regulator has issued a construction licence for unit 3 of the El Dabaa nuclear power plant, which will eventually house four Russian-supplied reactors. Construction of unit 3 is scheduled to begin in the coming months.
- Source: World Nuclear News
- Date: Saturday, 01 April 2023
- Original article: world-nuclear-news.org/Articles/Third-Egyptian-reactor-receives-construction-permi
The structure took 110 days to complete, 45 days ahead of schedule, Rosatom said. The containment acts as a hermetic protection system, designed to withstand high external and internal pressures and protect against radiation release.
In March 2022, workers completed welding of the main circulation pipeline connecting the reactor pressure vessel with the steam generators and the reactor coolant pumps.
- Source: Nucnet
- Date: Saturday, 11 March 2023
- Original article: nucnet.org/news/concrete-completed-for-containment-building-at-rooppur-1-vver-plant-3-5-2023
The launch of the two unit Rooppur NPP under construction in Bangladesh has been delayed by several months, according to the Chinese industry publication Polaris Electric News Network, citing representatives of the project. According to the latest plan, units 1 and 2 are now scheduled to be commissioned in February 2024 and late 2024. It was previously assumed that unit 1 would be put into operation in 2023 and unit 2 in 2024.
- Source: NEI Magazine
- Date: Saturday, 15 October 2022
- Original article: neimagazine.com/news/newsrooppur-npp-in-bangladesh-behind-schedule-10086555
The Engineering Division of Russia’s Rosatom, JSC Atomstroyexport (ASE), and the Korean Hydro and Nuclear Power Corporation (KHNP) have signed a contract for the construction of the turbine islands at the El Dabaa NPP project in Egypt. KHNP will construct about 80 buildings and structures at the NPP’s four units, and will purchase and supply equipment and materials for the turbine islands of the units. “The Turbine Islands deal concluded with ASE can be seen as a significant achievement for Korea, said KHNP President Hwang Joo-ho. “Based on our experience gained in the UAE, KHNP will make every effort to ensure the success of the El Dabaa NPP project.”
- Source: NEI Magazine
- Date: Wednesday, 31 August 2022
- Original article: neimagazine.com/news/newskhnp-to-supply-turbine-islands-for-rosatom-at-egypts-el-dabaa-npp-9965946
In a pressurised water reactor, the steam generators act as heat exchangers where water carrying heat generated from the nuclear reaction is used to turn demineralised water into steam. They are among the heaviest and largest components on the nuclear island.
Atomstroyexport, a subsidiary of Russian state nuclear corporation Rosatom, said the Kursk 2-1 project schedule is for the installation of all four steam generators and the reactor pressure vessel before the end of 2022.
- Source: Nucnet
- Date: Tuesday, 31 May 2022
- Original article: nucnet.org/news/first-steam-generator-installed-for-kursk-2-1-nuclear-power-plant-5-1-2022
Construction of unit 4 at the Xudapu nuclear power plant in China's Liaoning province has officially got under way with the pouring of first concrete for the reactor's nuclear island. The unit is the second of two VVER-1200 reactors at the site to be supplied by Russia.
- Source: World Nuclear News
- Date: Friday, 20 May 2022
- Original article: world-nuclear-news.org/Articles/Construction-of-Xudapu-4-under-way
The RPV, which weighs about 330 tonnes, is one of the largest reactor components, a vessel containing the nuclear reactor coolant, core shroud, and the reactor core and fuel.
Construction of the Generation III Kudankulam-3, a Russia-procured VVER- V-412, 917-MW pressurised water reactor, began in June 2017.
- Source: Nucnet
- Date: Saturday, 07 May 2022
- Original article: nucnet.org/news/rpv-installed-for-kudankulam-3-nuclear-power-plant-5-5-2022
Egypt's El Dabaa nuclear power project has moved forward with the application for construction licences for units 3 and 4. The application comes six months after the same step for units 1 and 2.
- Source: World Nuclear News
- Date: Thursday, 13 January 2022
- Original article: world-nuclear-news.org/Articles/Applications-made-to-build-El-Dabaa-units-3-and-4