Operators at the UK’s Sellafield site have removed the first zeolite skip from the First Generation Magnox Storage Pond (FGMSP) to a self-shielded box, which was then placed in the new Interim Storage Facility.
- Source: NEI Magazine
- Date: Friday, 29 March 2024
- Original article: neimagazine.com/news/newssellafield-begins-removal-of-zeolite-skips-from-legacy-pond-to-new-storage-11640320
The first of 237 zeolite skips has been removed from Sellafield's First Generation Magnox Storage Pond, which has been prioritised for clean-up by the UK's Nuclear Decommissioning Authority.
- Source: World Nuclear News
- Date: Thursday, 28 March 2024
- Original article: world-nuclear-news.org/Articles/First-zeolite-skip-removed-from-Sellafield-pond
Site holds 85% of all UK’s nuclear waste, much of which is stored in ageing facilities
- Source: Nucnet
- Date: Saturday, 17 February 2024
- Original article: nucnet.org/news/spending-watchdog-launches-investigation-into-risks-and-costs-2-5-2024
UK engineers from University of Glasgow, University of Manchester, Bristol Robotics Laboratory and Heriot-Watt University are developing the Symbiotic Multi-Robot Fleet (SMuRF) system, which could help with NPP decommissioning.
- Source: NEI Magazine
- Date: Thursday, 21 December 2023
- Original article: neimagazine.com/news/newscollaborating-robot-fleet-may-support-npp-decommissioning-11387398
The newly-opened Box Encapsulation Plant Product Store - Direct Import Facility at the Sellafield site in the UK has received its first box of historical radioactive waste.
- Source: World Nuclear News
- Date: Thursday, 21 December 2023
- Original article: world-nuclear-news.org/Articles/First-waste-received-by-new-Sellafield-transfer-fa
Teams of autonomous robots known as SMuRFs (for Symbiotic Multi-Robot Fleet) could assist in the future decommissioning of nuclear power plants, according to researchers from four British universities.
- Source: World Nuclear News
- Date: Tuesday, 19 December 2023
- Original article: world-nuclear-news.org/Articles/SMuRFs-to-help-in-nuclear-decommissioning
The Guardian newspaper has recently published two articles about the UK Nuclear Decommissioning Authority’s (NDA’s) Sellafield site, both of which have been strongly repudiated by Sellafield Ltd.
- Source: NEI Magazine
- Date: Friday, 08 December 2023
- Original article: neimagazine.com/news/newssellafield-repudiates-guardian-articles-on-cyber-attacks-and-leaks-11354910
A state-of-the-art Glove Box Training Facility for the UK nuclear industry has been opened at Sellafield. Glove boxes are crucial to operations at nuclear sites enabling operators to handle hazardous material in a safe and controlled environment. However, their use requires high levels of skill and dexterity. The new facility will reduce the amount of training done within plants and provide a standardised approach across the sector. It was delivered by the UK Alpha Resilience & Capability (ARC) programme.
- Source: NEI Magazine
- Date: Thursday, 12 October 2023
- Original article: neimagazine.com/news/newsstate-of-the-art-glove-box-training-facility-opens-at-sellafield-11210165
The defuelling of the first reactor at the UK’s Hunterston B NPP has been completed, on time and on budget, EDF Energy reported. Reactor 3 was defuelled in 16 months and work is due to start shortly on Reactor 4.
- Source: NEI Magazine
- Date: Friday, 22 September 2023
- Original article: neimagazine.com/news/newsdefuelling-of-first-reactor-complete-at-hunterston-b-11164076
The defueling of the first of two reactors at the Hunterston B advanced gas-cooled reactor (AGR) nuclear power plant in the UK has been completed on time and on budget, EDF Energy announced.
- Source: World Nuclear News
- Date: Friday, 22 September 2023
- Original article: world-nuclear-news.org/Articles/Fuel-removed-from-first-Hunterston-B-reactor