The US Department of the Air Force (DAF) has selected Eielson Air Force Base (AFB) to pilot its first micro-reactor. The next-generation energy capability will provide the installation with a clean, reliable, and resilient nuclear energy supply technology for critical national security infrastructure, the department said.

“Energy is a critical asset to ensure mission continuity at our installations,” said Deputy Assistant Secretary of the Air Force for Environment, Safety, and Infrastructure Mark Correll. “Micro-reactors are a promising technology for ensuring energy resilience and reliability, and are particularly well-suited for powering and heating remote domestic military bases like Eielson AFB.”

The micro-reactor pilot was initiated in response to the Fiscal Year 2019 National Defense Authorisation Act requirement to identify potential locations to site, construct, and operate a micro-reactor by the end of 2027. The micro-reactor will be commercially owned and operated and US Nuclear Regulatory Commission licensed. “This technology has the potential to provide true energy assurance, and the existing energy infrastructure and compatible climate at Eielson make for the perfect location to validate its feasibility,” said Correll.

He is working with the Air Force Office of Energy Assurance, the Office of the Deputy Assistant Secretary of Defense for Environment & Energy Resilience, the Department of Energy, and the Nuclear Regulatory Commission to facilitate the micro-reactor pilot, and to ensure this pilot is conducted with safety as the number one priority.

DAF said it is building energy resilience capabilites as a key enabler of mission success at its installations. Concurrently, the Department of Defense (DoD) is actively working to mitigate risks posed by climate change, and seeking energy sources that are reliable, resilient, and clean. To that end, the 2019 National Defense Authorisation Act (NDAA) required the Secretary of Energy to report on a pilot programme to provide resilience for DoD facilities by contracting with a commercial entity to build and operate at least one licensed micro- reactor by 31 December 2027. Building on this, Executive Order 13972, “Promoting Small Modular Reactors for National Defense and Space Exploration” outlined requirements for micro-reactor development specifically within the DoD.

The chronology is as follows:

September 2020: Request for Information (RFI) releasedDecember 2020: RFI responses receivedJuly 2021: Data gathering and environmental baselining site visitOctober 2021: Public Announcement of Eielson as chosen micro-reactor pilot locationFall 2021: Draft Request for Proposal (RFP) and compile environmental dataDecember 2021: RFP reviewsFebruary 2022: Release RFPLate 2022: Select vendor and release Notice of Intent to Award (NOITA)2022-2023: Begin permitting and licensing2024: Execute contract2025: Begin construction and pilot phase2026: Pre-operational testing2027: End pilot phase, enter commercial operation

The reactor technology has not yet been determined.

Photo: An F-35A Lightning II assigned to the 355th Fighter Squadron takes off from Eielson Air Force Base, Alaska (Photo credit: DOD)

Date: Saturday, 30 October 2021