Commercial operation of Generation III+ plant scheduled for 2021 The control room at the Leningrad 2-2 nuclear plant in Russia. Courtesy Rosatom. Russian nuclear regulator Rostekhnadzor has approved the next phase of commissioning at Unit 2 of the Leningrad 2 nuclear power station in Sosnovy Bor, western Russia.

The approval means the 1,085-MW Generation III+ pressurised water reactor, or VVER, has begun a gradual increase in capacity, from 1% to 35-40%.

That level will enable the turbine generator to be connected to the grid and begin generating and transmitting electricity to the country's network. Grid connection is scheduled for this autumn.

The plant, construction of which began in 2010, was brought to its minimum controlled power level and achieved first criticality in August.

Over the next six months the plant will go through the stages of power startup, pilot operation and comprehensive tests.

Leningrad 2-2, north of St Petersburg on the Gulf of Finland, will replace Leningrad-2, a 925-MW Soviet-designed light-water graphite reactor, or RBMK, which has been in commercial operation since February 1976 and is scheduled to be permanently shut down.

The identical Leningrad 2-1 unit, which began commercial operation in October 2018, replaced, Leningrad-1, which began commercial operation in November 1974 and was permanently shut down in December 2018. Leningrad-1 was also a Soviet-era RBMK.

Commissioning of Leningrad 2-2 will mean Russia’s fleet of Generation III+ units will increase to four. The others are Leningrad 2-1, Novovoronezh 2-1 and Novovoronezh 2-2.

According to International Atomic Energy Agency statistics, Russia has 38 nuclear power reactors in commercial operation and four under construction. In 2019 the nuclear fleet provided almost 20% of the country’s electricity production share.

Date: Thursday, 15 October 2020
Original article: nucnet.org/news/leningrad-2-2-moves-to-next-phase-of-commissioning-process-10-3-2020